Q: How do you create a test strategy? (Cont'd...)
Inputs for this process:
-
A description of the required hardware and software components, including test tools. This information comes from the test environment, including test tool data.
-
A description of roles and responsibilities of the resources required for the test and schedule constraints. This information comes from man-hours and schedules.
-
Testing methodology. This is based on known standards.
-
Functional and technical requirements of the application. This information comes from requirements, change request, technical and functional design documents.
-
Requirements that the system can not provide, e.g. system limitations.
Outputs for this process:
-
An approved and signed off test strategy document, test plan, including test cases.
-
Testing issues requiring resolution. Usually this requires additional negotiation at the
project management level.
[Continued on next page...]
|